LOCKED SCOPE DOCUMENT

v02 2026-03-04 CORRECTED Project: TechTown Acoustics 2.0 — MediaVerse Studio Complex, B3 Damascus

v02 corrects 7 values from v01: (1) North wall 614.8→860 cm, (2) Area 29.13→34.42 m², (3) Ceiling 290→350 cm, (4) Control Room NC-20→NC-25, (5) Video/Podcast NC-20→NC-25, (6) Samsung DVM→Daikin VRF, (7) Buffer spine NOT SELECTED→REQUIRED.

1. Project Identity

ProjectMediaVerse Acoustic Studio Complex
LocationTechTown Damascus, Basement Level 3 (B3)
ZoneYellow-highlighted area — Northwest corner of B3
Version2.0 (fresh start — v1.0 abandoned due to cross-LLM context loss)
DesignerThreefold Studio (architecture) + Obai (acoustic engineering)
Acoustic EngineerClaude Opus 4.6 (computational) under Obai's direction
Design StandardConservative / Broadcast-grade (highest tier)

2. Scope Boundary — CRITICAL (CORRECTED v02)

ONLY the yellow-highlighted zone in B3.png. NOT the full northwest trapezoid (~92 m² from Grok Session 2). NOT the 13-zone full floor analysis (Claude Web).
ShapeRight trapezoid — WIDENS going north
South wall (E-W)737 cm (7.37 m)
North wall (E-W)860 cm (8.60 m)
East wall (N-S)431 cm (4.31 m)
NW diagonal448 cm (4.48 m)
Gross area34.42 m²
Usable interior (after construction)~28–31 m² estimated
Ceiling height350 cm (floor to concrete slab) — gypsum T-bar at 290 cm is removable
Effective height (after treatment)~315 cm (floating floor -15cm, acoustic ceiling -20cm)
Raw volume120.5 m³
Effective volume~108.4 m³
v01 had north wall as 614.8 cm (area 29.13 m²). This was WRONG — the diagonal extends outward, making north wider than south. Corrected per MediaVerse.pdf authoritative dimensioned drawing showing 860 cm north wall.

3. Room Program — 5 Zones

5 ZONES: 4 separate rooms + buffer spine corridor. Live Room and Video/Podcast Studio are NOT combined/convertible.
RoomFunctionNC TargetRT60 TargetSTC TargetPriority
Voice-Over / Live RoomVO recording, voiceover, instrument trackingNC-150.15–0.25sSTC 58-68CRITICAL
Control RoomMixing, monitoring, session controlNC-250.30–0.40sSTC-55+CRITICAL
Video / Podcast StudioGreen screen shoots, podcast recording (2-3 people)NC-250.25–0.40sSTC-50+HIGH
Editing Area4 workstations, headphone-only monitoringNC-30–35≤ 0.50sSTC-40+MODERATE
Sound Lock + Buffer SpineDouble-door entry + service corridor between roomsNC-35N/ASTC-45+HIGH

Sight Line Requirements

RelationshipRequirement
Control Room → Live RoomMUST have direct visual sight line (observation window)
Control Room → Video/Podcast StudioNICE-TO-HAVE — secondary window or CCTV acceptable

4. Physical Constraints

Structural

ElementDetail
Foundation columns2 non-removable columns within the zone:
COL-1: 60 × 50 cm, center at (3.95, 1.36) from SW
COL-2: ~55 × 50 cm, center at (~7.10, 1.36), near/against east wall
Column row position111 cm from south wall, 270 cm from north wall
Internal partitionsALL demolished — full demolition confirmed

Wall Types & Isolation

WallTypeInherent STCThreat LevelNotes
NorthConcrete (exterior)STC-55+LOWFree mass — minimal additional treatment
EastGypsum (10 cm) to Server Room B313STC-25–30CRITICALHighest isolation priority. Server noise 55-65 dB(A) assumed worst-case
West/NWSlanted concrete (exterior facade)STC-55+MEDIUMFree mass, BUT VR Lab vibration risk from adjacent space
SouthInternal partition (to be rebuilt)TBDHIGHEntry side — sound lock required

Construction Constraints (Syria-specific)

5. HVAC System (CORRECTED v02)

SystemDaikin VRF (Variable Refrigerant Flow) — CANNOT be changed
Approach"Last mile" only — preserve VRF system, redesign final duct delivery
Primary unitU380 — near SE corner of zone (~6.88m E, ~0.50m N from SW)
StrategyOversize final drops, acoustic plenum boxes (50mm rockwool), inline silencers, flexible S-curve, terminal velocity ≤ 1.5 m/s
NC budgetHVAC must achieve NC-10 to NC-12 per duct run for NC-15 total in VO room

6. Acoustic Construction Specifications

ElementSpecificationApplies To
Room-within-a-room (box-in-box)Full decoupled shell constructionVO / Live Room (mandatory)
Floating floorNeoprene pads, f0 < 20 Hz targetVO / Live Room (mandatory)
Decoupled ceilingResilient hangers / spring isolatorsVO / Live Room (mandatory)
Mass-Air-Mass wallsDouble leaf with air gap, resonance below 50 HzAll studio walls
Observation windowsTriple-pane, angled 5°, different thicknessesControl Room walls
Acoustic doorsSTC-50+ rated, gasket sealedAll room entries
Green screenMotorized retractable (NOT permanent cyclorama)Video/Podcast Studio

7. Assumptions (Worst-Case)

ParameterAssumed ValueRationale
Server room noise (B313)55–65 dB(A)No measured data available — assume worst-case rack servers
Facade glazingSingle-pane float glass (worst STC)Glazing type unknown
Adjacent VR Lab vibrationPresent — structure-borneVR Lab west of the angled wall may generate low-frequency vibration
HVAC background noisePer Daikin VRF specs + regenerated noise calcNeed to verify duct velocities for NC contribution

8. Deliverables Checklist

#DeliverableFormatStatus
D1Full acoustic engineering calculations (RT60, NC, STC, modal analysis, Schroeder freq)HTML + PDFPending
D2Contractor-ready DXF drawings with layer structureDXFPending
D3Material BOM with local Syrian sources + import alternativesHTML + CSVPending
D4Interactive HTML review tool (layer toggles, specs)HTMLPending
D5HVAC noise mitigation plan with silencer scheduleHTML + DXFPending
D6Installation sequence / phasing document for contractorHTMLPending
D7Construction how-to guides: doors, windows, ceiling, walls, floors — per area, with charts and drawn multi-step instructionsHTML + SVG/PNGPending

9. Support Features (CORRECTED v02)

FeatureStatusNotes
South entrance sound lock / vestibuleCONFIRMEDDouble-door airlock entry
Buffer spine / service corridorREQUIREDConfirmed during cross-session review. Service corridor between rooms.

10. Occupancy & Operations

ParameterValue
Simultaneous occupancy4–6 people (2–3 editing + 2–3 in studio/control)
Editing stations4 workstations, headphones exclusively
Green screen typeMotorized retractable
Camera throw (video studio)~4.5 m depth target

11. Standards & References

12. v02 Change Log

#ChangeOld (v01)New (v02)Source
1North wall dimension614.8 cm (6.15 m)860 cm (8.60 m)MediaVerse.pdf
2Gross area29.13 m²34.42 m²Recalculated
3Ceiling height290 cm (T-bar grid)350 cm (to concrete slab)Cross-session data
4Control Room NCNC-20NC-25Cross-session data
5Video/Podcast NCNC-20NC-25Cross-session data
6HVAC systemSamsung DVM VRFDaikin VRFHVAC contractor
7Buffer spineNOT SELECTEDREQUIREDCross-session data

13. Sign-Off

This scope document is LOCKED as of 2026-03-04 (v02). Any changes require v03+ with change justification logged in CHANGELOG.