Construction Guides

Inspection Checkpoints

10-phase construction inspection gates with hold-point verification. Every phase must be signed off before the next begins.

BUILDER CUSTOMIZATION GUIDE -- INSPECTION CHECKPOINTS

CUSTOMIZABLE -- Inspection form template layout and company branding, reporting software or app used, inspector assignment and scheduling, photo documentation format, filing and archival method.

DO NOT ALTER -- Inspection criteria and pass/fail thresholds, hold-point sequence (no phase proceeds without sign-off), STC field-test requirements, NC measurement methodology, seal continuity verification steps, required test equipment specifications. All acoustic performance checkpoints are mandatory and must be completed as specified before proceeding to the next construction phase.

Inspection Legend

Understanding Inspection Types

H
Hold Point Work MUST STOP until inspector signs off. No subsequent trade can proceed.
W
Witness Point Inspector should be present but work can continue if notified 48h in advance.
Check Item Individual verification task within a phase. Each must be assessed Pass / Fail.

Phase Cards

Hold Point Summary

These 7 phases require mandatory sign-off before any subsequent work can proceed. No exceptions.

Phase Name # Checks Critical Tolerances Required Before Proceeding

Common Deficiencies

Most frequently observed defects grouped by inspection phase. Contractors should review these before requesting inspection.