Critical path installation order — acoustic isolation depends on correct sequencing. Every phase must be completed in order. Skipping or reordering steps will compromise the acoustic envelope.
CUSTOMIZABLE -- Scaffolding and temporary works supplier, site safety signage style, worker scheduling and shift patterns, tool brands, dust protection and site cleaning methods, delivery logistics and staging areas, progress reporting format.
DO NOT ALTER -- Phase sequence order (structural shell before floating floor before walls before ceiling before doors before treatment), hold-point inspection requirements, curing times between phases, seal-before-close protocol, STC verification testing at each stage. Changing the build order compromises acoustic isolation. Follow the sequence exactly as specified.
Visual timeline showing all phases with estimated durations. Total estimated: 6–8 weeks.
Complete each phase in order. Check off tasks as they are completed. Progress is saved automatically.
SSOT-GEOMETRY.html)
x=334, COL-E at x=727 from SW corner
X=206 west face, X=221 east face
350cm slab-to-slab)
400mm centers)
18mm, screw to pads only)
200mm)
10mm perimeter gap (isolate from walls!)
3mm deviation over 2m)
X=206–221, STC-55)
80×50cm, STC-53)
10mm gap + seal
400mm grid)
10mm gap all around)
100mm)
300×200mm) in ceiling plenum — ALL hangers must include neoprene isolation pads (no direct metal-to-slab suspension)
1500mm), B (1000mm), C (1000mm), D (500mm)
300mm minimum straight duct upstream AND downstream of every silencer — elbows or transitions at the silencer face reduce attenuation by 3–8 dB
1m flex)
3×)
220cm from floor (above camera line)
These sequencing rules are non-negotiable. Violating any of them compromises the acoustic isolation envelope.
Overlapping phases shown with dependencies. Critical path highlighted.
After each phase, perform these verification steps before proceeding.